Estimate at Completion (EAC) Calculator

The forecasted cost at the end of a project is the estimate at completion (EAC). In this calculator, the EAC is calculated based on the known values.

Calculate the Estimate at Completion (Forecasting Project Completion Cost)

The forecasted cost at the end of a project is the estimate at completion (EAC). In this calculator, the EAC is calculated based on the known values.

Code to add this calci to your website Expand embed code Minimize embed code

Formula:

EAC = AC + BUEC (For Scenario 1) EAC = BAC / CPI (For Scenario 2) CPI = EV / AC EAC = AC + (BAC - EV) (For Scenario 3) EAC = AC + ((BAC - EV) / ( CPI * SPI)) (For Scenario 4) SPI = EV / PV Where, EAC = Estimate at Completion BAC = Budget at Completion AC = Actual Cost BUEC = Bottom up Estimate to Complete CPI = Cost Performance Index EV = Earned Value AC = Actual Cost PV = Planned Value SPI = Schedule Performance Index

The forecasting project completion cost can be calculated as four scenarios with different values in each scenario.